CAPM Practice: Determine how to document project controls for an adaptive project
Question 35 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To inspect the team's process and identify improvements for the next iteration
Explanation
The Sprint Retrospective is an internal team event focused on process improvement. It's a control mechanism that ensures the team continuously improves how they work, reducing waste and improving quality.
**Why not B:** Reviewing completed stories with stakeholders happens in the Sprint Review.
**Why not C:** The retrospective focuses on process, not budget or schedule baselines.
**Why not D:** Presenting the increment to customers is the purpose of the Sprint Review.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).