Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 35 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

What is the main purpose of a Sprint Retrospective from a project controls perspective?
Show answer & explanation

Correct answer: To inspect the team's process and identify improvements for the next iteration

Explanation

The Sprint Retrospective is an internal team event focused on process improvement. It's a control mechanism that ensures the team continuously improves how they work, reducing waste and improving quality.

**Why not B:** Reviewing completed stories with stakeholders happens in the Sprint Review.

**Why not C:** The retrospective focuses on process, not budget or schedule baselines.

**Why not D:** Presenting the increment to customers is the purpose of the Sprint Review.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free