CAPM Practice: Determine how to document project controls for an adaptive project

An adaptive team tracks work using a physical or digital board with columns like 'To Do,' 'In Progress,' and 'Done.' This board is called:

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).