Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls for an adaptive project

Question 2 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team tracks work using a physical or digital board with columns like 'To Do,' 'In Progress,' and 'Done.' This board is called:
Show answer & explanation

Correct answer: A task board (or Scrum board)

Explanation

A task board (Scrum board or Kanban board) visualizes the status of work items as they flow through stages (To Do → In Progress → Done). It provides real-time visibility into what's being worked on, what's waiting, and what's complete. The board is typically visible to the entire team, promoting transparency and collaboration.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free