CAPM Practice: Determine how to document project controls for an adaptive project

Question 2 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team tracks work using a physical or digital board with columns like 'To Do,' 'In Progress,' and 'Done.' This board is called:
Show answer & explanation

Correct answer: A task board (or Scrum board)

Explanation

A task board (Scrum board or Kanban board) visualizes the status of work items as they flow through stages (To Do → In Progress → Done). It provides real-time visibility into what's being worked on, what's waiting, and what's complete. The board is typically visible to the entire team, promoting transparency and collaboration.

**Why not B:** A risk register documents identified risks, their analysis, owners, and planned responses. It does not track the flow of work items through stages like To Do, In Progress, and Done.

**Why not C:** A Gantt chart is a bar chart showing scheduled activities against a timeline, typically used in predictive planning. It does not organize work items into status columns.

**Why not D:** A velocity chart shows the amount of work (usually story points) completed per iteration over time. It measures team throughput rather than visualizing the current status of individual work items.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).