CAPM Practice: Determine how to document project controls for an adaptive project

Question 3 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

In Scrum, who is responsible for updating the sprint burndown chart?
Show answer & explanation

Correct answer: The development team, who are responsible for the sprint progress

Explanation

The development team owns and maintains the sprint burndown chart. They update it daily (typically after the daily standup) to reflect completed work. This daily update ensures the chart provides accurate, real-time progress information. The Scrum Master may facilitate this but the team owns the data and the chart.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).