In adaptive projects, the PRIMARY mechanism for tracking team progress during a sprint is:
Show answer & explanation

Correct answer: Burndown chart or burnup chart showing remaining work or completed work over time

Explanation

Burndown charts plot remaining work (story points or tasks) on the Y-axis against time (sprint days) on the X-axis. As the team completes work, the chart burns down toward zero. A burnup chart shows completed work growing toward the total scope. Both provide immediate visual transparency into sprint progress without bureaucratic overhead.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).