CAPM Practice: Determine how to document project controls for an adaptive project
Question 1 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Burndown chart or burnup chart showing remaining work or completed work over time
Explanation
Burndown charts plot remaining work (story points or tasks) on the Y-axis against time (sprint days) on the X-axis. As the team completes work, the chart burns down toward zero. A burnup chart shows completed work growing toward the total scope. Both provide immediate visual transparency into sprint progress without bureaucratic overhead.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).