CAPM Practice: Determine how to document project controls for an adaptive project
Question 1 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Burndown chart or burnup chart showing remaining work or completed work over time
Explanation
Burndown charts plot remaining work (story points or tasks) on the Y-axis against time (sprint days) on the X-axis. As the team completes work, the chart burns down toward zero. A burnup chart shows completed work growing toward the total scope. Both provide immediate visual transparency into sprint progress without bureaucratic overhead.
**Why not B:** A monthly status report is far too infrequent to track progress within a sprint that typically lasts one to four weeks. It is a predictive-style governance artifact for the sponsor, not a mechanism the team uses to see its own progress day to day.
**Why not C:** A detailed Gantt chart is a predictive scheduling tool built around planned task dependencies and dates. Updating one daily adds heavy overhead and does not reflect how adaptive teams track progress — by work remaining or completed, not by adherence to a detailed task schedule.
**Why not D:** Time sheets measure effort spent, not progress toward the sprint goal. A team can log many hours without completing any work items, so hours worked do not show how much work remains or has been delivered.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).