CAPM Practice: Determine how to conduct stakeholder communication
Question 54 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A peer review where the author (BA) presents requirements to a group of reviewers who examine them for completeness, correctness, and clarity — combining communication and validation in one event
Explanation
A structured walkthrough has the requirements author present their work to a review group. The author walks through the requirements; reviewers identify issues. This technique combines communication (the author explains the requirements) with validation (reviewers check quality) efficiently.
**Why not B:** A presentation technique using physical movement to engage audience attention describes a public speaking or facilitation technique, not a structured walkthrough. A structured walkthrough is a formal review session where the BA presents requirements to reviewers for quality inspection and feedback.
**Why not C:** Physically walking stakeholders through the project location describes a site tour, not a structured walkthrough. A structured walkthrough is a meeting-based review technique where the author walks through requirements documentation while reviewers examine it for completeness, correctness, and clarity.
**Why not D:** A walkthrough of completed software features with end users describes a demo or user acceptance review, not a structured walkthrough. Structured walkthroughs occur during the requirements phase before development, focusing on reviewing documentation rather than demonstrating working software.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).