CAPM Practice: Determine how to conduct stakeholder communication
Question 53 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Verbal communication conveys explicit content through words; non-verbal communication (body language, tone, facial expressions) conveys emotional context and credibility — a BA must read both to fully understand stakeholder concerns
Explanation
Research shows that non-verbal communication (body language, tone) often carries more meaning than words. A stakeholder saying 'Yes, that's fine' while crossing their arms and avoiding eye contact may not be truly agreeing. BAs who read non-verbal cues detect hidden concerns and skepticism that verbal responses miss.
**Why not A:** Non-verbal communication is highly relevant for business analysts. Body language, facial expressions, eye contact, and tone of voice convey critical information during stakeholder interactions. A BA who ignores non-verbal cues may miss signs of disagreement, confusion, or disengagement that stakeholders are not expressing verbally, leading to incomplete or inaccurate requirements.
**Why not B:** This answer incorrectly reverses the definitions. Verbal communication refers to spoken words and oral exchanges, while written communication is a separate category. Non-verbal communication encompasses body language, gestures, facial expressions, posture, and tone of voice. Confusing these categories demonstrates a fundamental misunderstanding of communication theory.
**Why not D:** Verbal and non-verbal communication are not identical and serve distinct purposes. Verbal communication conveys explicit content and factual information through words, while non-verbal communication conveys emotions, attitudes, emphasis, and relational dynamics. Effective BAs understand how to read and use both channels together, as non-verbal signals can reinforce, contradict, or add nuance to verbal messages.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).