CAPM Practice: Determine how to conduct stakeholder communication
Question 9 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Any barrier that distorts or interferes with the intended message — including ambiguous language, jargon, cultural differences, or emotional reactions
Explanation
Communication noise is any interference that distorts the message between sender and receiver. In BA work, this includes technical jargon alienating business stakeholders, cultural differences in directness, or emotional triggers that prevent objective reception of requirements.
**Why not B:** While literal background noise can impede communication, the concept of "communication noise" in business analysis is much broader. It encompasses any factor that distorts message transmission — including psychological, semantic, and cultural barriers — not just audible interference during meetings.
**Why not C:** Communication volume refers to the quantity of messages, not to noise. High volume can contribute to information overload, but noise specifically refers to distortions or barriers that prevent the intended meaning from being received accurately, regardless of how many messages are sent.
**Why not D:** Including irrelevant information is one possible source of noise, but this answer is far too narrow. Communication noise also includes ambiguous language, jargon, cultural misunderstandings, emotional reactions, and many other barriers that interfere with clear message transmission between sender and receiver.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).