CAPM Practice: Determine how to conduct stakeholder communication

Question 10 of 67 in Determine how to conduct stakeholder communication

Pick an answer below — you'll get the explanation instantly, no signup.

What is a 'stakeholder register' used for in communication planning?
Show answer & explanation

Correct answer: A project document capturing stakeholder identification, interests, influence levels, communication needs, and engagement status

Explanation

The stakeholder register is the foundational document for stakeholder management. It captures who the stakeholders are, their roles, interest, power/influence, communication preferences, and current engagement level — guiding communication planning.

**Why not A:** A stakeholder register is an internal project management document, not a legal filing with any government body. It serves as a practical tool for the project team to track and manage stakeholder relationships, and it carries no legal or regulatory significance.

**Why not B:** A stakeholder register is a proactive planning tool, not a reactive complaint log. It captures stakeholder information, interests, and engagement strategies before issues arise. Complaint tracking would be handled by a separate issues or risk log.

**Why not C:** A stakeholder register does not track compensation or financial payments. It documents stakeholder attributes like influence, interest, communication preferences, and engagement levels to support effective communication planning and stakeholder management.

Key Concept

This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).