CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 2 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The technical blocker is an issue; the vendor delivery concern is a risk
Explanation
An issue is a problem that is currently happening and requires immediate attention (the technical blocker exists now). A risk is an uncertain event that may or may not occur in the future (the vendor may or may not deliver late). This distinction is fundamental to project management.
**Why not A:** Constraints are limiting factors imposed on the project (such as budget or regulatory requirements), not current problems or future uncertainties. The technical blocker is an active problem (an issue), and the vendor concern is a future uncertainty (a risk) — neither fits the definition of a constraint.
**Why not C:** Not both items are risks. The technical blocker is currently happening and actively blocking work, making it an issue requiring immediate attention. Only the vendor delivery concern qualifies as a risk because it involves future uncertainty that may or may not materialize.
**Why not D:** The technical blocker is not a constraint — it is an active problem (an issue) that the team is currently experiencing. The vendor concern is not an assumption because it is not something believed to be true for planning; it is an uncertain future event (a risk) that could affect the project.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).