CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 1 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Explain that ongoing maintenance is operations work, not part of the project scope
Explanation
Projects are temporary endeavors with a defined beginning and end, while operations are ongoing and repetitive. Once the point-of-sale system is implemented and transitioned, the project ends. Ongoing maintenance is operational work, not project work.
**Why not B:** Adding ongoing maintenance to the project charter would blur the boundary between project work and operational work. Projects are temporary with defined endpoints, and the charter should reflect only the project scope — not perpetual operational activities that have no end date.
**Why not C:** Scheduling maintenance activities as a project phase incorrectly treats ongoing operational work as part of the temporary project. Maintenance is continuous and repetitive by nature, which makes it fundamentally different from project phases that have defined start and end points.
**Why not D:** Accepting the request would be incorrect because ongoing software maintenance is operational work, not part of the implementation project. The project ends when the system is implemented and transitioned to operations; maintenance continues indefinitely under operational management.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).