CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 49 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A program contains related projects managed in a coordinated way to obtain benefits, while a portfolio groups projects, programs, and operations to achieve strategic objectives
Explanation
A program is a group of related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually. A portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic business objectives. The key distinction is that programs focus on coordinated management of related work for specific benefits, while portfolios focus on strategic alignment and prioritization.
**Why not A:** Duration is not the primary distinguishing characteristic. While programs may be shorter than some portfolios, the key distinction is about purpose and composition: programs coordinate related projects for benefits, while portfolios align work to strategic objectives.
**Why not B:** Both programs and portfolios have their own management roles. A program has a program manager, and a portfolio has a portfolio manager. The distinction is not about which management title is required but about the scope and strategic alignment of each.
**Why not D:** Neither programs nor portfolios are defined by focusing on a single management area like cost or schedule. Programs focus on coordinated benefit delivery from related projects, while portfolios focus on strategic alignment and prioritization of the organization's investments.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).