CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 48 of 95 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A risk is something that might happen in the future, while an issue is a problem that currently exists
Explanation
A risk is an uncertain event or condition that, if it occurs, has an effect on project objectives. It is future-oriented (may or may not happen). An issue is a current problem or concern that exists now and requires resolution. This is the fundamental distinction between the two concepts.
**Why not A:** Neither risks nor issues are specifically tied to schedule or budget domains. Both can affect any project objective including scope, quality, resources, or stakeholder satisfaction. The distinction is about timing (future vs. current), not knowledge area.
**Why not C:** This reverses the urgency relationship. Issues require immediate attention because they are current problems. Risks require proactive planning but may not need immediate action since they are future uncertainties that may or may not materialize.
**Why not D:** Risks can be positive (opportunities) or negative (threats). Issues are generally problems that need resolution, though the scenario focuses on the timing distinction. The characterization that risks are always negative is incorrect.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).