CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 91 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Social awareness, by recognizing the emotional state of the team member
Explanation
Social awareness involves recognizing and understanding the emotions, needs, and concerns of others. Mariana recognized the team member's emotional state (being upset) and responded appropriately by acknowledging perspectives and allowing time to decompress.
**Why not A:** Self-management involves controlling one's own emotional responses, such as managing personal frustration or stress. While Mariana may have exercised self-management by staying calm, her primary action was recognizing the team member's emotional state, which is social awareness.
**Why not B:** Technical competence involves understanding the subject matter of the disagreement. Mariana's response was driven by her ability to read emotional cues, not by her understanding of the technical details being debated.
**Why not D:** Risk management involves identifying and responding to potential threats to project objectives. While team conflict could be a project risk, Mariana's action was specifically about recognizing and responding to an individual's emotional state in the moment, which is an emotional intelligence skill, not a risk management activity.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).