CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 90 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Leadership focuses on inspiring and motivating people toward a vision, while management focuses on planning and controlling work
Explanation
Leadership emphasizes inspiring, motivating, and guiding people toward achieving a vision or goal, while management focuses on planning, organizing, directing, and controlling work and resources to achieve objectives.
**Why not A:** This reverses the concepts. Leadership deals with interpersonal relationships, vision, and inspiration, while management deals with planning and controlling work, which may include technical decision frameworks. Leadership is people-oriented, not technically oriented.
**Why not B:** Leadership is not restricted to senior executives. Project managers, team leads, and individual contributors can all exercise leadership. Leadership is a set of behaviors and skills, not a role limited to organizational hierarchy.
**Why not D:** This reverses the relationship. Leadership can be exercised without formal authority through influence and inspiration. Management typically relies on formal authority to organize, direct, and control work and resources.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).