CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 20 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The project sponsor should approve the additional budget request
Explanation
The project sponsor is responsible for providing financial resources and has the authority to approve budget increases. This is a key distinction between sponsor and project manager responsibilities.
**Why not B:** The functional manager manages the team member's department but typically does not have authority over the project budget. Budget approval for project resources falls within the project sponsor's domain, not the functional manager's.
**Why not C:** The project team executes work but does not have authority to approve budget increases. Financial decisions of this nature require sponsor-level authorization, as the sponsor is accountable for the project's financial resources.
**Why not D:** Reallocating funds from other project activities without sponsor approval could compromise other deliverables. Budget increases require proper authorization from the sponsor, not unilateral reallocation by the project manager.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free