CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 21 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitator
Explanation
A facilitator helps the team work through issues, explore options, and reach agreement. Declan is guiding the discussion process to help the team reach consensus.
**Why not A:** A coach focuses on developing individual team members' skills and capabilities over time. Declan is not mentoring or developing anyone here — he is guiding a group discussion toward consensus, which is a facilitation activity.
**Why not B:** A negotiator works to reach agreements between parties with competing interests, often involving trade-offs or compromises on resources, contracts, or scope. The team members are debating a technical approach, not negotiating competing interests or resource allocation.
**Why not C:** An initiator starts or proposes new ideas, projects, or processes. Declan is not introducing something new — he is helping the team work through an existing disagreement to reach agreement.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).