CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 19 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Provides day-to-day direction to the project team → Project Manager 2. Authorizes funding and approves the project charter → Project Sponsor 3. Performs the technical work and creates deliverables → Project Team 4. Removes high-level organizational obstacles beyond the PM's authority → Project Sponsor
Explanation
The project manager handles daily execution and direction. The project sponsor provides executive support, funding authorization, charter approval, and removes organizational barriers. The project team performs the actual work to create deliverables. While senior management may be involved in governance, the sponsor specifically removes obstacles and provides authorization in this context.
**Why not B:** This option incorrectly assigns day-to-day direction to the project team and technical work to the project manager. The project team performs technical work and creates deliverables, while the project manager provides daily direction and coordination. These two roles are swapped.
**Why not C:** This option incorrectly assigns day-to-day direction to the project sponsor and removing organizational obstacles to the project manager. The sponsor operates at a higher level providing strategic support and removing barriers, while the project manager handles daily execution. These responsibilities are reversed.
**Why not D:** This option incorrectly assigns day-to-day direction to the sponsor, charter authorization to the team, technical work to the sponsor, and removing organizational obstacles to the project manager. Every pairing is wrong — the sponsor does not perform technical work or provide day-to-day direction to the team, and the team does not authorize funding.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).