CAPM Practice: Demonstrate an understanding of project management planning

Question 9 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup.

Match each planning component on the left with its primary purpose on the right. Items: 1. Cost Baseline 2. Quality Management Plan 3. Risk Register 4. Schedule Baseline Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Cost Baseline → Defines the time-phased budget used to measure cost performance 2. Quality Management Plan → Establishes metrics and standards to ensure deliverables meet requirements 3. Risk Register → Documents identified risks, their analysis, and planned responses 4. Schedule Baseline → Provides the approved project timeline used to monitor progress

Explanation

The cost baseline is the time-phased budget against which cost performance is measured. The quality management plan defines how quality requirements will be met and deliverables will be verified. The risk register documents all identified risks and their management approach. The schedule baseline is the approved version of the schedule used as a reference for monitoring progress and changes.

**Why not B:** This option swaps the cost baseline with the risk register and the quality management plan with the schedule baseline. Risk documentation belongs to the risk register, not the cost baseline. Timeline monitoring belongs to the schedule baseline, not the quality management plan.

**Why not C:** This option incorrectly assigns quality metrics to the cost baseline, risk documentation to the quality management plan, timeline monitoring to the risk register, and cost measurement to the schedule baseline. All four pairings are incorrect.

**Why not D:** While the quality management plan and risk register are correctly matched, the cost baseline and schedule baseline descriptions are swapped. The cost baseline measures cost performance (not timeline), and the schedule baseline monitors progress over time (not cost).

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).