Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of project management planning

Question 8 of 100 in Demonstrate an understanding of project management planning

Haruki Kessler is planning resources for a mobile app development project at Quartile Advisory. The project requires 3 developers for 6 months, 1 designer for 3 months, and 1 tester for 4 months. What is the total number of resource months needed?
Show answer & explanation

Correct answer: 25 resource months

Explanation

Total resource months = (3 developers × 6 months) + (1 designer × 3 months) + (1 tester × 4 months) = 18 + 3 + 4 = 25 resource months. This calculation helps determine resource capacity and cost planning.

**Why not A:** 13 resource months would result from incorrect calculation. The correct formula multiplies each resource count by its duration: (3x6) + (1x3) + (1x4) = 18 + 3 + 4 = 25, not 13.

**Why not B:** 5 resource months for 6 months ignores the need to multiply resource quantity by duration. Simply adding the headcount (3+1+1=5) without accounting for how long each works does not capture total effort.

**Why not C:** 14 resource months is an incorrect calculation. Applying the correct formula of quantity times duration for each resource type yields (3x6) + (1x3) + (1x4) = 25, not 14.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free