CAPM Practice: Demonstrate an understanding of project management planning

Question 10 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup.

Maryam Ogawa is closing a project at Harvest Market Co that was terminated early due to budget constraints. Several team members are concerned about being reassigned before documenting lessons learned. What should Maryam do FIRST?
Show answer & explanation

Correct answer: Conduct a lessons learned session with the team before reassignment to capture critical knowledge

Explanation

Even when projects are terminated early, capturing lessons learned is a critical closure activity that should occur while team members are still available and details are fresh. This knowledge benefits future projects and is an essential part of project closure, regardless of the reason for closure.

**Why not A:** Archiving documents and moving to contract closure skips the critical step of capturing lessons learned while team members are still available. Once the team disperses, valuable knowledge about what went well and what could improve will be lost.

**Why not B:** Releasing all team members immediately to minimize costs would result in losing the opportunity to capture important project knowledge. Even with budget constraints, the short-term cost of a lessons learned session is far outweighed by the long-term organizational value of captured knowledge.

**Why not D:** Waiting for all team members to be available in the future is impractical and risks losing critical knowledge. Memories fade over time, team members may leave the organization, and the details of what happened become less reliable. Lessons learned should be captured while information is fresh.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).