CAPM Practice: Demonstrate an understanding of project management planning
Question 16 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To identify, analyze, and develop response strategies for potential threats and opportunities
Explanation
Risk planning aims to proactively identify risks (both threats and opportunities), analyze their potential impact and probability, and develop appropriate response strategies. This allows the project team to be prepared rather than reactive.
**Why not A:** Assigning blame is never the purpose of risk planning. Risk planning is a proactive, forward-looking process focused on preparing the team to handle uncertainty, not a reactive exercise to attribute fault for materialized risks.
**Why not C:** Eliminating all risks is unrealistic and not the goal of risk planning. Some risks cannot be fully eliminated, and risk planning recognizes this by developing response strategies that reduce probability, minimize impact, or accept certain risks with contingency plans.
**Why not D:** Documenting past risks from previous projects is part of lessons learned and organizational process assets, not the primary purpose of risk planning. Risk planning focuses on current project threats and opportunities, though historical data may inform the process.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).