CAPM Practice: Demonstrate an understanding of project management planning
Question 17 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone represents a significant point in the project with zero duration, while task duration is the time required to complete an activity
Explanation
A milestone is a significant checkpoint or event in a project schedule that has zero duration—it marks the completion of a phase or deliverable. Task duration, by contrast, represents the actual time needed to complete a specific work activity.
**Why not A:** Milestones and task durations are fundamentally different concepts, not the same thing used in different methodologies. A milestone is a zero-duration point in time, while task duration is a measurable period — this distinction applies across all project management methodologies.
**Why not B:** A milestone is not longer than a task duration — it has zero duration. A milestone marks a significant point or event in the schedule. While it may be associated with the completion of multiple tasks, it does not encompass or contain them; it simply marks when they are complete.
**Why not D:** Milestones do not require resources to complete because they have zero duration — they are markers, not work activities. Task durations do require resources, as they represent the actual time and effort needed to complete work. This option reverses the relationship entirely.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free