CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 31 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Brainstorming generates many ideas without initial judgment, while focus groups gather perspectives on specific topics from representative participants
Explanation
Brainstorming is a creative technique focused on generating a large quantity of ideas without criticism or judgment during the ideation phase. Focus groups are moderated discussions with representative stakeholders to explore opinions, attitudes, and reactions to specific topics or products.
**Why not B:** Neither brainstorming nor focus groups require or exclude external facilitators. Both can be facilitated internally or externally. The distinction is about their purpose: brainstorming generates ideas freely, while focus groups gather perspectives on specific topics.
**Why not C:** Brainstorming primarily produces qualitative data (ideas and concepts), not quantitative data. Both techniques produce qualitative insights, though their methodologies and objectives differ in how those insights are gathered.
**Why not D:** Both brainstorming and focus groups can be used in any project approach — agile, predictive, or hybrid. There is no restriction tying either technique to a specific project management methodology.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).