CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Question 32 of 105 in Demonstrate an understanding of common problem-solving tools and techniques

Pick an answer below — you'll get the explanation instantly, no signup.

Halima Menon facilitated a two-hour problem-solving meeting at Vector Aerospace to address recurring quality issues. Three team members dominated the discussion while four others barely spoke. The meeting ran 30 minutes over, and no decisions were made. When evaluating this meeting's effectiveness, what is the PRIMARY concern?
Show answer & explanation

Correct answer: Halima failed to achieve balanced participation and reach actionable outcomes

Explanation

The primary measures of meeting effectiveness are achieving the meeting's purpose and ensuring productive participation. This meeting failed on both counts: it didn't reach decisions (no outcomes) and had unbalanced participation. A facilitator must ensure all voices are heard and that meetings produce actionable results.

**Why not A:** Suggesting a focus group format does not address the core issues of unbalanced participation and lack of decisions. A focus group is a different technique with a different purpose, and switching formats would not resolve the facilitation failures that occurred.

**Why not C:** While a structured problem-solving framework could help, the primary concern is the failure to achieve the meeting's basic purpose: balanced participation and actionable outcomes. The lack of a framework is a contributing factor, not the primary concern.

**Why not D:** Exceeding the scheduled duration by 30 minutes is a symptom, not the primary concern. The fundamental issues are that the meeting failed to produce decisions and that participation was dominated by only three of seven attendees.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).