CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 41 of 85 in Demonstrate an understanding of a project management plan schedule
Show answer & explanation
Correct answer: Activity list, activity attributes, and activity duration estimates
Explanation
The Develop Schedule process uses: the activity list (what activities exist), activity attributes (details about each activity), and activity duration estimates (how long each takes) — along with resource requirements, resource calendars, and project assumptions — to construct the project schedule.
**Why not B:** The risk register and stakeholder register provide important context for project planning but are not direct inputs that define activities, sequencing, or duration estimates. They support risk-informed scheduling but do not contain the core scheduling data.
**Why not C:** The WBS and WBS dictionary define the project scope and deliverables but do not include activity-level details like sequencing or duration estimates. The WBS feeds into the Define Activities process, which then produces the activity list used in Develop Schedule.
**Why not D:** The project charter and business case establish high-level objectives and justification for the project but do not contain the detailed activity definitions, sequences, or duration estimates needed as direct inputs to the Develop Schedule process.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).