CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 40 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The schedule should be set at 140 days to have an 80% confidence of meeting the deadline, or schedule risk should be explicitly documented and contingency reserve added
Explanation
Monte Carlo simulation reveals that the deterministic critical path underestimates actual duration risk — there is only a 30% chance of meeting the 120-day estimate. To have 80% confidence, 140 days is needed. The appropriate response is either to: (1) set the baseline at 140 days with appropriate contingency, or (2) acknowledge the risk with the sponsor and add a schedule contingency reserve of 20 days, documenting the risk explicitly.
**Why not B:** Cancelling the project because of a 30% probability is an overreaction. Monte Carlo simulation is a risk analysis tool designed to inform planning decisions, not a pass/fail test. The appropriate response is to adjust the schedule or add contingency, not abandon the project.
**Why not C:** Setting the baseline at the deterministic 120-day critical path ignores the simulation's findings. A 30% probability of completion means there is a 70% chance of missing that date, making it an unreliable baseline that would likely result in schedule overruns.
**Why not D:** Dismissing the Monte Carlo simulation as wrong contradicts sound risk management practice. The simulation uses probabilistic analysis to account for real-world uncertainty, and its results should inform planning rather than be ignored in favor of a single deterministic estimate.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).