CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 42 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: $48,000
Explanation
Expected cost of fast tracking = 40% probability × $120,000 rework cost = $48,000. Comparing: Crashing: certain cost of $80,000. Fast tracking: expected cost of $48,000 (but with uncertainty). The expected cost of fast tracking is lower, but crashing provides certainty. The choice depends on the organization's risk tolerance and whether the 40% rework scenario would be catastrophic or manageable.
**Why not A:** The expected cost of fast tracking is not $0. While the direct cost is $0, there is a 40% probability of incurring $120,000 in rework. Expected monetary value (EMV) accounts for both the probability and the financial impact: 40% x $120,000 = $48,000.
**Why not C:** $120,000 represents the full rework cost if the risk materializes, not the expected cost. Since there is only a 40% chance of the rework occurring, the expected cost is 40% of $120,000 = $48,000. Using the full amount would overstate the expected financial impact.
**Why not D:** $80,000 is the cost of crashing, not the expected cost of fast tracking. The expected cost of fast tracking is calculated using EMV: 40% probability multiplied by the $120,000 rework cost equals $48,000, which is lower than the $80,000 crashing cost.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free