CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 25 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Estimates the duration of individual activities and rolls them up to create the overall project duration
Explanation
Bottom-up estimating builds the schedule from the activity level — estimating each individual work package or activity, then aggregating these estimates upward through the WBS to arrive at the total project duration. It is more accurate than top-down methods but takes more time and information to perform.
**Why not A:** Using historical data from similar projects describes analogous estimating (top-down), not bottom-up estimating. Analogous estimating works from the project level down, while bottom-up estimating works from individual activities up.
**Why not B:** Using expert judgment to estimate overall duration in one step describes a top-down or rough order of magnitude approach. Bottom-up estimating specifically requires decomposing work into individual activities and estimating each one separately.
**Why not D:** Applying a mathematical formula based on project parameters describes parametric estimating, which uses statistical relationships between variables to calculate estimates. Bottom-up estimating is detail-driven, not formula-driven.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).