Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of a project management plan schedule

Question 26 of 85 in Demonstrate an understanding of a project management plan schedule

What does the term 'lead' mean in the context of project scheduling?
Show answer & explanation

Correct answer: The amount of time a successor activity is accelerated relative to its predecessor

Explanation

A lead allows a successor activity to start before its predecessor is complete. For example, in an FS relationship with a -5 day lead (sometimes written as a negative lag), the successor can start 5 days before the predecessor finishes. Leads accelerate the schedule by allowing overlap, while lags add delay between activities.

**Why not A:** This confuses the scheduling term "lead" with the organizational role of leading a team. In scheduling, "lead" is a specific technical term describing the acceleration of a successor activity relative to its predecessor, not the project manager's leadership role.

**Why not B:** The first activity in a project network is simply the starting activity or the project start milestone. It has no special designation as a "lead" in scheduling terminology.

**Why not C:** A delay added between activities to allow for drying or curing time describes a "lag," not a "lead." Lags add waiting time between activities, while leads accelerate successor activities by allowing them to start before their predecessor finishes. They are opposite concepts.

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free