Skip to content
PMPCAPM

Baselines (Scope, Schedule, Cost)

A baseline is the approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

Share:

Know it well enough for the exam? Questions on Baselines (Scope, Schedule, Cost) are scenario-based, not definitional.

Practice it free

Explanation

The project management plan includes three primary baselines: the scope baseline, the schedule baseline, and the cost baseline. Together, they form the performance measurement baseline, which is the integrated scope-schedule-cost plan against which project execution is compared to measure and manage performance.

The scope baseline consists of the project scope statement, the work breakdown structure (WBS), and the WBS dictionary. It defines the total scope of the project and what deliverables will be produced. The schedule baseline is the approved version of the schedule model, identifying the planned start and finish dates for all project activities. The cost baseline is the approved time-phased project budget, excluding management reserves, used to measure cost performance.

Baselines serve as the reference point for the Monitoring and Controlling Process Group. Actual performance is compared against baselines to calculate variances, identify trends, and forecast future performance. Any change to a baseline must go through Perform Integrated Change Control and be formally approved. Once approved, the baseline is updated (re-baselined) and all future comparisons use the new baseline.

Key Points

  • •Three primary baselines: scope, schedule, and cost
  • •Approved versions used as the basis for performance comparison
  • •Can only be changed through formal change control
  • •Together form the performance measurement baseline

Exam Tip

Baselines can only be changed through Perform Integrated Change Control. If actual performance deviates from the baseline, you analyze the variance and decide on corrective action — you do NOT simply update the baseline without approval.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Predictive Life Cycle (Waterfall)

A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.

Subsidiary Plans

Subsidiary plans are the individual management plans that are components of the overall project management plan, each addressing a specific Knowledge Area or management function.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

PM Fundamentals & Frameworks

Study full domain →

Practice Baselines (Scope, Schedule, Cost)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.