Share (Opportunity Strategy)
Share is an opportunity response strategy that allocates ownership of an opportunity to a third party who is best able to capture the benefit for the project. It is the opportunity equivalent of the threat strategy "transfer."
Know it well enough for the exam? Questions on Share (Opportunity Strategy) are scenario-based, not definitional.
Practice it freeExplanation
The share strategy involves partnering with or delegating to another entity that has the expertise, technology, or resources to maximize the opportunity. The project shares in the benefits without bearing full responsibility for making the opportunity happen.
Common examples include forming joint ventures, creating partnerships, establishing teaming agreements, or using special-purpose companies. For instance, a construction firm might share an opportunity to use a new building technology by partnering with a specialist firm that has expertise in that technology, splitting the resulting cost savings.
Sharing is appropriate when the project team alone cannot fully capitalize on the opportunity but a third party can. The arrangement typically includes a sharing of both the investment and the benefits. Like all risk response strategies, the sharing arrangement, terms, and risk owner should be documented in the risk register.
Key Points
- •Allocates opportunity ownership to a third party best positioned to capture benefits
- •Mirrors the "transfer" strategy for threats
- •Common tools: joint ventures, partnerships, teaming agreements
- •Benefits are typically shared between the project and the third party
Exam Tip
Share for opportunities mirrors Transfer for threats. If a question involves partnering with another organization to capture a benefit, the answer is share.
Frequently Asked Questions
Related Topics
Risk Response Strategies for Opportunities
Risk response strategies for opportunities are the five approaches used to address positive risks: exploit, enhance, share, accept, and escalate. Each strategy aims to increase the probability, impact, or both of a beneficial risk event.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Exploit (Opportunity Strategy)
Exploit is an opportunity response strategy that ensures the positive risk is realized by eliminating the uncertainty associated with the opportunity. It is the most aggressive opportunity strategy.
Plan Risk Responses
Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Share (Opportunity Strategy)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.