Skip to content
PMPCAPM

Control Procurements

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Control Procurements is the process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts.

Share:

Know it well enough for the exam? Questions on Control Procurements are scenario-based, not definitional.

Practice it free

Explanation

Control Procurements ensures that both the buyer and seller meet their contractual obligations. The project manager and procurement team review seller performance, manage contract changes through the integrated change control process, and resolve any disputes or claims that arise during contract execution.

Key activities include performance reviews comparing seller deliverables to contract requirements, inspections and audits, payment administration, and claims management. The process uses tools such as earned value analysis, trend analysis, and contract change control systems to track and manage procurement performance.

This process also encompasses contract closure, where the team verifies that all work and deliverables are acceptable, settles any open claims, and archives contract documentation for future reference. In PMBOK 6th Edition, Close Procurements was merged into Control Procurements.

Key Points

  • •Belongs to the Monitoring & Controlling process group
  • •Manages contract performance, changes, and dispute resolution
  • •Includes contract closure activities (merged from Close Procurements)
  • •Uses performance reviews, inspections, and earned value analysis

Exam Tip

In PMBOK 6th Edition, Close Procurements was folded into Control Procurements. If the exam asks about closing contracts, the answer is Control Procurements.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Procurement Management

Study full domain →

Practice Control Procurements

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.