PMP Practice: Identify and Analyze Conflict Sources
Question 1 of 10 in Manage Conflicts
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a separate working session with Amara and Elif to explore their underlying interests, establish shared goals around the product launch, and collaboratively adjust the backlog prioritization criteria to balance user value with campaign timing
Explanation
This scenario tests conflict management using a collaborative approach when stakeholders have competing priorities and communication has broken down. The conflict stems from both a substantive disagreement (feature priorities) and a process failure (Amara not being included in refinement). The project manager's role is to facilitate resolution by helping stakeholders understand each other's interests and find a mutually beneficial path forward. By creating a separate working session, Juniper can de-escalate the public tension, allow both parties to be heard without an audience, and guide them toward shared objectives. The key is addressing both the immediate prioritization dispute and the underlying engagement gap that allowed marketing to be excluded from planning. A collaborative approach seeks win-win outcomes rather than imposing authority or deferring the decision. The closing fact that developers are visibly uncomfortable signals that the public conflict is affecting team morale and must be handled constructively and soon.
**Why not A:** Pausing the sprint review to have the team vote on features inappropriately puts a prioritization dispute to a democratic process in a public setting. Backlog prioritization is a product owner responsibility in agile, and forcing a vote in front of the team would further escalate the tension and potentially undermine the product owner's authority.
**Why not B:** Documenting and escalating to the executive sponsor defers the conflict rather than resolving it. The project manager has the skills and responsibility to facilitate resolution between stakeholders before resorting to escalation, especially when the root cause includes a process gap (marketing not being invited to refinement).
**Why not D:** Reminding the marketing director that the product owner has final authority is technically correct but dismissive of his legitimate business concerns. This approach would likely provoke the threatened escalation and damage the working relationship, while failing to address the underlying engagement gap that excluded marketing from planning.
Key Concept
This question covers Identify and Analyze Conflict Sources under Manage Conflicts (People).