PMP Practice: Determine communication methods, channels, frequency, and level of detail
Question 2 of 5 in Manage Communications
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Create a communications management plan that identifies stakeholder information needs, communication methods, frequency, and responsible parties
Explanation
With over 40 diverse stakeholders having different information needs, technical knowledge levels, and communication preferences, Lila must first analyze these needs and create a structured approach to managing communications. A communications management plan documents who needs what information, when they need it, in what format, and through which channels. This ensures tailored, effective communication that meets each stakeholder group's specific requirements. For example, warehouse workers might need daily shift briefings about operational impacts, while executives need monthly dashboards showing overall progress. The plan prevents both information overload for some stakeholders and information gaps for others. This structured approach is essential in predictive projects with diverse stakeholder groups, ensuring communication supports project success rather than creating confusion or resistance.
**Why not A:** Scheduling weekly status meetings with all 40+ stakeholders wastes time for those who only need monthly summaries and provides insufficient detail for those needing daily updates. A one-size-fits-all meeting schedule does not address the varying information needs, technical understanding levels, and communication preferences described in the scenario.
**Why not B:** Distributing detailed technical documentation to all stakeholder groups ignores the varying levels of technical understanding. Warehouse workers and union representatives have different information needs than IT staff. This approach would likely overwhelm non-technical stakeholders while still not addressing timing and format preferences.
**Why not C:** Sending a single kickoff email and waiting for stakeholders to request updates is a reactive, pull-based approach that shifts the communication burden to stakeholders. Many stakeholders may not know what information they need or when, leading to communication gaps. Effective project communication requires a proactive, planned approach.
Key Concept
This question covers Determine communication methods, channels, frequency, and level of detail under Manage Communications (Process).