PMP Practice: Determine training options based on training needs
Question 2 of 4 in Ensure Team Members/Stakeholders Are Adequately Trained
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Work with Marcus and the training vendor to design a blended approach that includes condensed two-day on-site sessions with pre-work modules and post-training virtual coaching, addressing both operational constraints and learning effectiveness
Explanation
This scenario tests the project manager's ability to navigate stakeholder resistance while maintaining training effectiveness and protecting project objectives. Karim faces a classic stakeholder conflict: the VP of Operations has legitimate operational concerns and significant project influence, but his proposed solution contradicts validated training needs. The best approach is collaborative problem-solving that honors both the training effectiveness requirements and the operational constraints. Working with Marcus and the training vendor to design a blended solution demonstrates servant leadership, stakeholder engagement, and creative problem-solving. A condensed on-site component with supporting virtual elements can preserve the essential hands-on practice and collaboration while reducing operational disruption. This approach maintains the relationship with a powerful stakeholder, addresses his legitimate concerns, and still meets the fundamental training requirements identified in the needs assessment. The closing fact that Marcus controls budget approval for the next phase makes relationship preservation critical, while the vendor's confirmation that video-only learning is inadequate makes full compromise unacceptable.
**Why not B:** Escalating immediately without attempting to resolve the conflict collaboratively damages the relationship with a key stakeholder who has legitimate operational concerns and significant project influence. While escalation may eventually be necessary, it should not be the first response when creative problem-solving options remain unexplored. This approach treats the situation as win-lose rather than seeking mutual benefit.
**Why not C:** Accepting an approach that the training needs assessment and vendor have both identified as ineffective compromises project success. While documenting risk is appropriate, knowingly accepting an inadequate training approach when alternatives exist fails the project manager's responsibility to advocate for project success. Written acknowledgment does not mitigate the actual performance impacts that will occur.
**Why not D:** Proceeding without addressing Marcus's concerns ignores a powerful stakeholder's legitimate operational issues and risks damaging a critical relationship. While the original plan is supported by the needs assessment, inflexibility when faced with valid constraints demonstrates poor stakeholder management. This approach may be technically correct but politically tone-deaf, potentially jeopardizing budget approval and sponsor support.
Key Concept
This question covers Determine training options based on training needs under Ensure Team Members/Stakeholders Are Adequately Trained (People).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions