PMP Practice: Promote the Shared Vision
Question 9 of 20 in Develop a Common Vision
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a collaborative session where the team and Min-Ji review user data, crash reports, and velocity trends together to build consensus on balancing stability improvements with feature delivery
Explanation
When team members have conflicting views on priorities, the project manager's role is to facilitate alignment around a common understanding of value and risk. By bringing the team and product owner together to review objective data—user impact, crash reports, velocity trends—Ember creates transparency that allows everyone to see the full picture. This collaborative approach helps the group understand the root cause of the disagreement: Min-Ji is focused on market visibility while the team sees technical risk threatening long-term success. The data-driven conversation enables the team to co-create a vision that balances short-term marketing needs with technical sustainability, which is essential for shared commitment. Agile teams function best when decisions emerge from collective understanding rather than authority or compromise.
**Why not A:** Splitting the team into two tracks divides resources and may reduce the quality and velocity of both efforts. A small team working on two parallel tracks risks delivering neither effectively, especially when the stability issues affect 30% of users and could undermine the credibility of new features at the conference.
**Why not B:** Deferring to the product owner's authority and coaching the team to ignore technical concerns dismisses the architect's legitimate warning that technical debt will slow future sprints dramatically. The 30% crash rate is a serious user-facing issue, and overriding technical judgment with positional authority undermines team trust.
**Why not D:** Siding with the development team and advocating for postponing cosmetic features entirely ignores the product owner's legitimate business constraint of the conference in four weeks. The PM should facilitate collaborative problem-solving, not unilaterally override the product owner's business judgment.
Key Concept
This question covers Promote the Shared Vision under Develop a Common Vision (People).