PMP Practice: Communicate risk status to stakeholders
Question 4 of 5 in Assess and Manage Risks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: $93,500
Explanation
Expected Monetary Value is calculated by multiplying each possible outcome by its probability and summing the results. For this contaminated soil risk: ($45,000 × 0.20) + ($85,000 × 0.50) + ($140,000 × 0.30) = $9,000 + $42,500 + $42,000 = $93,500. This EMV represents the statistically weighted average cost if this risk occurs, and should inform how much contingency reserve Kavya allocates. EMV calculations help project managers make informed decisions about risk response investments by quantifying uncertain events into single values for comparison and budgeting purposes.
**Why not A:** This represents simply averaging the three cost estimates ($45,000 + $85,000 + $140,000) ÷ 3 = $90,000, which ignores the different probabilities of each scenario occurring. Equal weighting is incorrect when probabilities differ.
**Why not B:** This results from swapping the best-case and worst-case probabilities: ($45,000 × 0.30) + ($85,000 × 0.50) + ($140,000 × 0.20) = $13,500 + $42,500 + $28,000 = $84,000. EMV requires pairing each scenario with its own probability.
**Why not D:** This is the most likely cost estimate alone ($85,000), but EMV requires considering all scenarios weighted by their probabilities, not just selecting the single most probable outcome. Using only the most likely value underestimates the risk impact from the high-cost scenario.
Key Concept
This question covers Communicate risk status to stakeholders under Assess and Manage Risks (Process).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions