CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 1 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: High uncertainty exists about requirements and frequent stakeholder feedback is needed to guide direction
Explanation
Adaptive approaches are designed for high-uncertainty environments where requirements emerge through work and feedback. When stakeholders can't fully articulate what they want upfront, or when the right solution requires discovery through iteration, adaptive methods allow the project to learn and adjust direction based on each cycle's results.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).