CAPM Practice: Explain when it is appropriate to use an adaptive approach
Question 2 of 61 in Explain when it is appropriate to use an adaptive approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Requirements that are expected to evolve based on user feedback and market conditions
Explanation
Evolving requirements are the defining indicator for adaptive approaches. When requirements will change based on user feedback, market learning, or discovery, adaptive methods' iterative cycles allow the team to incorporate new knowledge into each subsequent iteration — creating a built-in mechanism for change that predictive methods lack.
**Why not B:** Fixed regulatory requirements that cannot change are stable and known up front, which favors a predictive approach. Adaptive methods' built-in mechanism for change offers little benefit when the requirements will not change.
**Why not C:** A well-understood process that has been repeated many times has low uncertainty. The work can be planned in detail up front, which is where predictive approaches perform well.
**Why not D:** Sequential physical construction with detailed specifications is a classic predictive scenario. The specifications are defined early, late changes are costly, and the work does not lend itself to frequent incremental delivery and feedback.
Key Concept
This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).