CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 2 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Show answer & explanation
Correct answer: A regulatory environment requiring extensive documentation and formal approvals
Explanation
Regulated industries (construction, pharmaceuticals, aerospace, government contracting) often mandate extensive documentation, formal stage-gate approvals, and traceability — characteristics that align naturally with predictive methodologies. The structured, document-heavy nature of predictive approaches satisfies compliance and audit requirements.
**Why not A:** Short project duration with minimal stakeholder involvement does not inherently favor predictive methodology. Predictive approaches are chosen based on requirement stability and regulatory needs, not project duration or stakeholder involvement level.
**Why not C:** Vague requirements expected to emerge over time are the opposite of what predictive methodology requires. When requirements are unclear and evolving, adaptive or iterative approaches are more appropriate because they accommodate changing scope.
**Why not D:** High novelty with no historical precedent favors adaptive approaches where the team can learn and adjust through iterations. Predictive approaches work best when the work is well-understood, not when the team is exploring entirely new territory.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free