CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

Question 1 of 85 in Explain when it is appropriate to use a predictive, plan-based approach

Pick an answer below — you'll get the explanation instantly, no signup.

A predictive, plan-based project management approach is MOST appropriate when:
Show answer & explanation

Correct answer: Requirements are well-understood, stable, and unlikely to change significantly

Explanation

Predictive (waterfall) approaches work best when requirements are well-defined, stable, and can be fully specified upfront. When changes are unlikely and the path to the final product is clear, predictive planning allows for efficient, sequential execution with detailed upfront planning.

**Why not A:** Team distribution across time zones is a logistical consideration that affects communication planning, not methodology selection. Both predictive and adaptive projects can have distributed teams; geography alone does not determine the appropriate approach.

**Why not C:** Frequently changing customer requirements are a strong indicator for adaptive methodology, not predictive. Predictive approaches assume stable requirements that can be fully defined upfront; frequent changes would undermine the front-loaded planning model.

**Why not D:** Cutting-edge technology with many unknowns creates high uncertainty that predictive planning cannot effectively address. When the path to the solution is unclear, iterative discovery through adaptive methods is more appropriate than comprehensive upfront planning.

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).