CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
Question 33 of 85 in Explain when it is appropriate to use a predictive, plan-based approach
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Project X: adaptive; Project Y: predictive
Explanation
Project X (uncertain market fit, novel product, inexperienced team) has high uncertainty and unknown requirements — classic indicators for adaptive. Discovery and iteration are needed. Project Y (documented procedures, experienced team, fifth repetition, regulatory requirements) has stable, known requirements and compliance demands — classic indicators for predictive. Methodology selection should match the uncertainty profile of each project.
**Why not A:** Assigning Project X to predictive and Project Y to adaptive reverses the correct methodology alignment. Project X's high uncertainty and novel product development call for adaptive, while Project Y's documented procedures and regulatory requirements call for predictive.
**Why not B:** Using adaptive for both projects ignores Project Y's characteristics. Project Y has documented procedures, an experienced team, five prior repetitions, and regulatory compliance requirements — all strong indicators for predictive methodology. Not every project benefits from adaptive approaches.
**Why not D:** Using predictive for both projects ignores Project X's high uncertainty and novel nature. A fixed timeline alone does not justify predictive methodology. Project X's uncertain market fit and inexperienced team with the product type require the discovery and flexibility that adaptive approaches provide.
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).