What distinguishes a 'release plan' from an 'iteration plan' in adaptive project planning?
Show answer & explanation

Correct answer: A release plan forecasts what will be delivered across multiple iterations; an iteration plan commits to work for one iteration

Explanation

A release plan takes a longer view, identifying which backlog items will be delivered in which release across several iterations. An iteration plan is more granular, committing to specific items for one iteration.

**Why not B:** Neither release plans nor iteration plans are categorically mandatory or optional in the abstract — their use depends on team practice and organizational context. Scrum requires sprint planning but does not mandate a formal multi-sprint release plan in every engagement; calling one mandatory and the other optional misrepresents both.

**Why not C:** In agile practice both plans are created collaboratively. Release planning typically involves the product owner, team, and key stakeholders working together; iteration planning is conducted by the whole team including developers. Assigning each plan to a different organizational stratum contradicts the cross-functional, self-organizing nature of agile teams.

**Why not D:** The distinction between release and iteration plans is about time horizon and granularity, not about budget versus scope. Both levels of planning address scope — which features and stories will be delivered; budget is managed at the portfolio or program level and is not the differentiating factor between these two plan types.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).