CAPM Practice: Explain the components of an adaptive plan
Question 28 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: It is the evolving, prioritized list of all work needed to achieve the product vision
Explanation
The product backlog is the core planning artifact in adaptive projects. It's dynamic — continuously refined, reprioritized, and updated — making it the single source of truth for what work remains.
**Why not A:** The backlog does not replace the charter, which authorizes the project.
**Why not B:** The Product Owner orders the backlog; the Scrum Master does not assign tasks.
**Why not C:** The backlog evolves through refinement; it is not fixed at kickoff.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).