CAPM Practice: Explain the components of an adaptive plan

Question 18 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive planning, what is the key difference between 'planning poker' and traditional expert estimation?
Show answer & explanation

Correct answer: Planning poker surfaces team-wide perspectives through simultaneous voting, while traditional expert estimation relies on one or few experts whose anchoring effect can suppress others' estimates

Explanation

Traditional expert estimation suffers from anchoring bias: when one expert states an estimate, others tend to align with it even if they privately disagree. Planning poker prevents this by having all estimators reveal their estimates simultaneously, before discussion. Outlier estimators (highest and lowest) then explain their reasoning, surfacing assumptions and domain knowledge that improve the collective estimate.

**Why not A:** Planning poker is not necessarily faster than expert estimation — it often takes more time due to discussion rounds after revealing estimates. Its advantage is not speed but accuracy and inclusiveness, as it prevents anchoring bias and surfaces diverse perspectives.

**Why not C:** This reverses the typical usage. Planning poker commonly uses relative units like story points, while traditional expert estimation often uses hours or days. Planning poker's strength is in relative comparison, not hour-based estimation.

**Why not D:** Planning poker is effective with any team size — it is not limited to large teams. It is commonly used with standard Scrum teams of 5-9 people. The key benefit is simultaneous estimation regardless of team size, not that it requires many estimators.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).