CAPM Practice: Explain the components of an adaptive plan

Question 19 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

An organization is implementing adaptive planning for the first time. The team struggles because the product owner cannot prioritize the backlog — every item is 'highest priority.' What technique BEST helps?
Show answer & explanation

Correct answer: Use relative ranking or priority frameworks (e.g., MoSCoW, Weighted Shortest Job First) to force explicit comparisons between items and establish an ordered, not just classified, backlog

Explanation

'Everything is highest priority' is a common PO struggle, often resulting from fear of committing to explicit trade-offs. Forced ranking techniques help: MoSCoW (Must have, Should have, Could have, Won't have) requires the PO to categorize each item. Weighted Shortest Job First (WSJF) scores items on value, risk, and job size to produce an objective ordering. These frameworks make trade-offs explicit, helping the PO articulate real priorities rather than avoiding difficult decisions.

**Why not B:** Removing all 'highest priority' labels and starting over with no priorities does not address the underlying problem—the PO's reluctance to make explicit trade-offs. Without a structured technique that forces comparisons between items, the PO is likely to recreate the same 'everything is highest priority' backlog.

**Why not C:** Assigning priority numbers randomly produces an ordering with no connection to business value, risk, or urgency. The team could spend sprints building low-value items, and this approach avoids rather than resolves the PO's need to make real priority decisions.

**Why not D:** Ordering the backlog is the product owner's accountability because the PO represents business value and stakeholder needs. Shifting prioritization to the team removes that business perspective; the better path is to equip the PO with techniques that make trade-offs explicit.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).