CAPM Practice: Explain the components of an adaptive plan

Question 34 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

Which planning horizon is MOST appropriate for detailed iteration-level planning in an adaptive project?
Show answer & explanation

Correct answer: The next iteration only

Explanation

Detailed planning in adaptive projects focuses on the near term — the next iteration. Plans become progressively less detailed further out (rolling wave planning), acknowledging that details will become clearer over time.

**Why not A:** Planning 12 months of detailed work contradicts adaptive principles. Detailed plans degrade in accuracy over longer horizons because requirements, priorities, and conditions change. Adaptive projects maintain a detailed plan only for the near term.

**Why not C:** A calendar quarter is too far out for detailed iteration-level planning. While quarterly planning may be appropriate for release-level or strategic planning, detailed task assignment and capacity planning should focus on the upcoming iteration to maintain accuracy.

**Why not D:** Planning the entire lifecycle in detail upfront is a predictive (waterfall) approach. Adaptive projects acknowledge that future conditions are uncertain and plan in detail only for what is imminent, using progressively coarser detail for later periods.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).