CAPM Practice: Explain the components of an adaptive plan

Question 33 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

What is a 'Minimum Viable Product' (MVP) in adaptive project planning, and why is it important?
Show answer & explanation

Correct answer: The smallest set of features that delivers value and enables validated learning from customers

Explanation

An MVP is the smallest product that can be released to real users to test assumptions and gather feedback. It's central to adaptive planning because it maximizes learning per unit of investment and reduces risk of building the wrong thing.

**Why not A:** An MVP refers to the product, not the team. Team size is a resourcing decision and does not define the minimum feature set released to customers.

**Why not B:** An MVP is not defined by cost. The cheapest version of a product may not deliver value or generate useful learning; the MVP is the smallest set of features that does both.

**Why not C:** An MVP is not a quality threshold. It reduces scope, not quality — the features delivered should still be fit for use so that customer feedback is meaningful.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).