CAPM Practice: Explain the components of an adaptive plan
Question 42 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Release roadmap
Explanation
A release roadmap provides a forward-looking view of planned features across releases or iterations. It communicates strategic intent without over-committing to detailed plans that will need to change.
**Why not A:** Daily standup notes capture day-to-day task status within a single iteration. They do not provide a high-level view of features across multiple iterations or releases — they are an operational coordination tool, not a strategic planning artifact.
**Why not B:** The Definition of Done is a quality agreement that specifies what criteria must be met for work to be considered complete. It does not contain schedule information or feature sequencing across releases.
**Why not D:** Team working agreements define how team members collaborate (communication norms, meeting schedules, coding standards). They address team process, not the strategic sequencing of features across future releases.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).