CAPM Practice: Explain the components of an adaptive plan
Question 41 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Welcome the change, update the product roadmap and backlog priorities to reflect the new business reality
Explanation
Adaptive projects embrace responding to change over following a plan. Business priority changes should be reflected in the backlog immediately. This responsiveness is a core agile value and competitive advantage.
**Why not A:** An approved roadmap is not a fixed baseline in adaptive work; rejecting the change ignores the new business reality.
**Why not C:** Continuing with the old plan until after the release delays value and keeps the team working on outdated priorities.
**Why not D:** Waiting for a quarterly formal change review adds unnecessary delay; the product owner can reprioritize the backlog continuously.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).